Monday, January 28, 2013

MMC Projects - Volunteers Needed



TIMELINE            MISSIONS MOBILIZATION CENTER PROJECTS
Feb. & Mar.           V.C.T. Tile Laying
Feb. & Mar.           Heating & Air Installation
Feb. & Mar.           Drywall Hanging & Finishing
Feb. & Mar.           Drop in Ceiling Installation
Feb. & Mar.           Painting
Apr. & May            Painting
Apr. & May            Flooring Installation
Apr. & May            Floor Finishing
Apr. & May            Wood Base Molding Installation
Apr. & May            Door Hanging & Painting
Contact Mark LeMay at (615) 812-6959 or David Acres at (615) 373-2255 if you can assist.

MMC Photos as of Jan. 2013











Tuesday, May 08, 2012


TIMELINE            MISSIONS MOBILIZATION CENTER PROJECTS

ASAP                    Sheetrock finisher for 2 shower rooms


ASAP                    Ceiling grid installer (drop ceiling) –all warehouse enclosure


May 15 on             Electrician (run conduit, install boxes) – office complex


Anytime                 Cleanout tool trailer – sort and inventory tools


Anytime                 Carpenter – building 100’ wall, sheetrock


ASAP                    Metal window installers (9 in warehouse)


Anytime                 Sheet metal worker (trim around exterior windows)


Anytime                 Sort, clean up DR equipment and material (warehouse)


Anytime                 Plumber (complete rough in – office complex)


Anytime                 Painter (paint exterior rollup door, exterior doors)


ASAP                    Local volunteer to mow, weed eat weekly (water plants)


Anytime                 Cabinet maker


Anytime                 Volunteer construction coordinator to oversee completion of facility


Contact Mark LeMay at (615) 812-6959 or Carl Lord at (615) 892-0734 if you can assist.

Wednesday, March 14, 2012


Contact Carl Lord to volunteer to work on the Missions Mobilization Center in Mount Juliet by calling 615-892-0734!

Tuesday, February 14, 2012

Insulation installers and sheetrock hangers are needed for the month of March. Contact Carl Lord to volunteer by calling (615) 892-0734.
MMC PROGRESS AS OF FEBRUARY 14, 2012

Monday, October 31, 2011

Progress is really being made at the MMC! Concrete was poured in the administrative side this weekend, volunteers have recently completed the manmade stone facade on parts of the building's exterior, and stud walls are going up in the warehouse for showers, utility rooms, etc! Sign your volunteer group up today to be a part of this progress!


Thursday, September 01, 2011

Concrete pour for th MMC is finished! Look at the progress!






















Monday, August 22, 2011

Excitement is building at the Missions Mobilization Center! The concrete was poured in buildnig on Saturday, August 20!


















EXCITEMENT is building at the Missions Mobilization Center! The concrete was poured in the building on Saturday, August 20!



















Tuesday, July 19, 2011







Volunteers from Bellevue Bapitst Church, Cordova, are working on the Missions Mobilizatio Center this week to apply the stone to the facade.






















































Thursday, March 17, 2011


March 17, 2011 - Windows being installed in the MMC by volunteer labor! Thank you, Tennessee Baptists!


Friday, March 11, 2011

Please be in prayer for those impacted by the Japan earthquake today. Tennessee Baptist Disaster Relief leadership is monitoring the situation closely.

Based on the SBDR International Response plan, Baptist Global Response (BGR) will take the initial lead in assessing the situation and how Southern Baptists can best respond. BGR has Baptist partners in the area who are moving to assess the damage even now. It is unknown at this point if volunteers will be needed. If so, AL is the first state convention on call during March. TN is the first state on call during the month of May each year. However, a large volunteer response may necessitate trained personnel from multiple states being involved in the effort.

Your Tennessee Baptist Disaster Relief staff will continue to keep you informed on this situation. More detailed information, as it is available will be posted to TBC website, www.tnbaptist.org.

Monday, March 07, 2011

Check out the latest pics of the Missions Mobilization Center! Volunteers continue to work through these cold months!






Friday, January 07, 2011

Volunteers have been working diligently to enclose the MMC so work can be done on the inside this winter. Look at the progress! The neon green color is where the contrasting stone will be installed once funds are available to purchase the supplies.




Thursday, January 06, 2011

Progress is being made on the house at the MMC site in Mount Juliet! Look what's been done in the last month!





Monday, November 01, 2010

October 28-30-2010, more than 30 volunteers from several different associations in West TN worked to lay brick for the Mission House located on the MMC property! How exciting to drive up and see the progress! Thank you, Beulah Baptist Association volunteers for the beautiful job you did on the house!






10-29-10 Front entrance of the Mission House








10-29-10 Rear view of the Mission House

Monday, October 25, 2010

10-25-10 MMC Building Progress

















Tuesday, October 12, 2010









The roof of the MMC is being intalled!

Monday, September 27, 2010

Not only are we building the new Missions Mobilization Center (MMC), but we are remodeling a home on the property to serve as a bunkhouse for volunteers working on the MMC. Here's a big shout out to volunteers from Long Hollow Baptist Church for installing the new windows so we can brick the house! Pics will be posted on the Mission House Photos page!